A 4.6-acre landfill must be evaluated for
Chapter , Problem 16-49(choose chapter or problem)
A 4.6-acre landfill must be evaluated for economicviability. As part of the costbenefit analysis, thecost to extract and treat the landfill gas must bedetermined.Using the following, design a landfill gasextraction system and estimate the cost to implementsuch a system:Landfill dimensions are 1000 feet by 200 feet.Area of influence of a landfill gas extractionwell is a 50-foot radius.Cost of well construction is $3000 each.Cost of wellhead (necessary for each well) is$2500 each.Cost of collection header piping 8diameterHDPE is $35/linear foot.Cost of condensate knockouts (located at lowpoints) is $5000 each.Cost of blower/flare station is $500,000.