37E Suppose we have five jobs with specified required
Chapter 3, Problem 37E(choose chapter or problem)
?37E Suppose we have five jobs with specified required times and deadlines: ?t?1 = 25, d?1 = 50; ?t?3 = 15, ?d?2 = 60; ?t?3 = 20, ?d?3 = 60; ?t?4 =5, ?d?4 = 55; ?t?5 = 10, ?d?5 = 75. Find the maximum lateness of any job when the jobs are scheduled in this order (and they start at time 0): Job 3, Job 1, Job 4, Job 2, Job 5. Answer the same question for the schedule Job 5, Job4, Job 3, Job I, Job 2.