Hawkins Construction Co. has a $60 million contract to
Chapter 18, Problem 15(choose chapter or problem)
Hawkins Construction Co. has a $60 million contract to construct a highway overpass and cloverleaf. The total estimated cost for the project is $50 million. Costs incurred in the first year of the project are $8 million. Hawkins Construction Co. appropriately uses the percentageof-completion method. How much revenue and gross profit should Hawkins recognize in the first year of the project?