Chapter 3, Problem 3.32(choose chapter or problem)
El Paso Water is planning to install wind turbinesto provide enhanced evaporation of reverse osmosisconcentrate from its inland desalting plant. Thecompany will spend $1.5 million in year 1 and $2million in year 2. Annual maintenance is expectedto cost $65,000 per year through year 10. Determinethe equivalent annual cost of the project inyears 1 through 10 at an interest rate of 6% peryear. Also, develop a single-cell spreadsheet functionto display the total A value.