Suppose that the construction of a solar power station is
Chapter 4, Problem 191E(choose chapter or problem)
Suppose that the construction of a solar power station is initiated. The project’s completion time has not been set due to uncertainties in financial resources. The completion time for the
first phase is modeled with a beta distribution and the minimum, most likely (mode), and maximum completion times for the first phase are 1.0, 1.25, and 2.0 years, respectively. Also, the meantime is assumed to equal \(\mu=1+4(1.25)+2) / 6=1.333\). Determine the following in parts (a) and (b):
(a) Parameters α and β of the beta distribution.
(b) Standard deviation of the distribution.
(c) Sketch the probability density function.
Equation transcription:
Text transcription:
mu=1+4(1.25)+2) / 6=1.333
Questions & Answers
QUESTION:
Suppose that the construction of a solar power station is initiated. The project’s completion time has not been set due to uncertainties in financial resources. The completion time for the
first phase is modeled with a beta distribution and the minimum, most likely (mode), and maximum completion times for the first phase are 1.0, 1.25, and 2.0 years, respectively. Also, the meantime is assumed to equal \(\mu=1+4(1.25)+2) / 6=1.333\). Determine the following in parts (a) and (b):
(a) Parameters α and β of the beta distribution.
(b) Standard deviation of the distribution.
(c) Sketch the probability density function.
Equation transcription:
Text transcription:
mu=1+4(1.25)+2) / 6=1.333
ANSWER:Answer
Step 1 of 3
(a)
The complete time for the first phase is modeled with a beta distribution and the minimum, most likely (mode), maximum completion times for the first phase are respectively.
Also the mean time assumed to equal,
We are asked to determine the parameters for the beta distribution.
We have given
We have the formulas for mean and mode when above situation is given,
These equations can be solved for parameters to obtain
Therefore,