A bulldozer pushes 1000 lbm of dirt 300 ft with a force of
Chapter 3, Problem 253EUP(choose chapter or problem)
QUESTION:
Problem 253EUP
A bulldozer pushes 1000 lbm of dirt 300 ft with a force of 400 lbf. It then lifts the dirt 10 ft up to put it in a dump truck. How much work did it do in each situation?
Questions & Answers
QUESTION:
Problem 253EUP
A bulldozer pushes 1000 lbm of dirt 300 ft with a force of 400 lbf. It then lifts the dirt 10 ft up to put it in a dump truck. How much work did it do in each situation?
ANSWER:
Solution 253 EUP
Step 1 of 3:
In this question, we need to find work done in each situation
Data given
Mass of dirt
Distance moved by pushes
Force
Height moved by dirt