A community plans to build a facility to convert solar radiation to electrical power. The community requires 1.00 MW of power, and the system to be installed has an efficiency of 30.0% (that is, 30.0% of the solar energy incident on the surface is converted to useful energy that can power the community). Assuming sunlight has a constant intensity of 1 000 W/m2, what must be the effective area of a perfectly absorbing surface used in such an installation?
Questions & Answers
QUESTION:
A community plans to build a facility to convert solar radiation to electrical power. The community requires 1.00 MW of power, and the system to be installed has an efficiency of 30.0% (that is, 30.0% of the solar energy incident on the surface is converted to useful energy that can power the community). Assuming sunlight has a constant intensity of 1 000 W/m2, what must be the effective area of a perfectly absorbing surface used in such an installation?
ANSWER:Step 1 of 3
Efficiency is given by,
Implies,
..........(1)